A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work is further increased by 50%?

IAS 2021CSAT Maths

2021mcqmedium

A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work is further increased by 50%?

Official previous-year question

Prelims CSAT (Paper II) · Held on 10 Oct 2021.

Options

  1. A22
  2. B21
  3. C18
  4. D15