The problem requires determining the individual time Ram takes to complete the entire job. This can be calculated by first establishing the combined and individual work rates.
- Ram and Shyam together complete 60% of the job in 4 days. Their combined one-day work rate is 10060×41=203 of the job.
- The remaining 40% of the job is completed by Shyam alone in 8 days. Therefore, Shyam's one-day work rate is 10040×81=201 of the job.
- If Shyam completes 201 of the job in one day, he would take 20 days to complete the entire job alone.
- Let Ram's one-day work rate be x1 and Shyam's one-day work rate be y1. From the above, we know y1=201.
- The combined one-day work rate is x1+y1=203.
- Substituting Shyam's rate into the combined rate equation: x1+201=203.
- Solving for x1: x1=203−201=202=101.
- Therefore, Ram's one-day work rate is 101 of the job, which implies Ram would take 10 days to complete the entire job alone.
Incorrect Options
Options 1 (6 days), 2 (8 days), and 4 (11 days) are incorrect as the calculated time for Ram to complete the entire job alone is 10 days.