A and B, working separately can do a piece of work in 12 days and 20 days respectively. If they work alternately, beginning with A, then in how many days can the work be completed?
Held on 14 May 2025 · Verified 13 Jul 2026.
15
15/2
14/2
14
Sign in to track your attempts and accuracy.
Sign in to keep a private note on this question. Nothing you write is ever public.
X, Y and Z together can do a piece of work in 16 (4/11) days. X and Y together can do the same work in 20 days. In how many days will Z alone finish the 60% of the work?
If the mean of five observations x + 1, x + 2, x + 3, x + 4 and x + 5 is 15, then what is the mean of the first three observations?
Amit is walking at a speed of 10 km/hr. After every kilometer, he takes a rest for 5 minutes. What is the time taken to cover a distance of 5 kilometers by Amit?
The difference between cost price (CP) and selling price (SP) of an article is Rs 240. If the profit is 20%, then the selling price is
Consider the following frequency distribution. | Class | 0-10 | 10-20 | 20-30 | 30-40 | 40-50 | 50-60 | 60-70 | |---|---|---|---|---|---|---|---| | Frequency | 4 | 5 | 7 | 10 | 12 | 8 | 4 | Find the median of the distribution?
Work through every CUET UG Arithmetic PYQ, year by year.