A and B together complete the job in 24 days, so their combined rate is 241 of the job per day.
A alone completes the job in 32 days, so A's rate is 321 of the job per day.
B's rate = (A and B together) - (A alone)
B′s rate=241−321
Finding common denominator (LCM of 24 and 32 is 96):
=964−963
=961 of job per day
Therefore, B alone takes 96 days to complete the full job.
Both A and B worked together for 8 days.
Work done=241×8
=248
=31
They completed 31 of the job in 8 days.
Remaining work=1−31
=32
B works alone on the remaining work. B's rate is 961 per day.
Time=32÷961
=32×96
=3192
=64 days
Therefore, B will take 64 days to complete the remaining job.