A: 41 in 12 days means full work in 48 days. B: 50% in 20 days means full in 40 days. C: 31 in 15 days means full in 45 days. B finishes earliest.
A can do 41th part of work in 12 days, B can do 50% work in 20 days , and C can do 31rd of the same work in 15 days. Who complete the work first?
Held on 26 Aug 2022 · Verified 13 Jul 2026.
A will complete first
B will complete first
'A', 'B' and 'C' will complete the work at the same time
'C' will complete first
Sign in to track your attempts and accuracy.
Sign in to keep a private note on this question. Nothing you write is ever public.
X, Y and Z together can do a piece of work in 16 (4/11) days. X and Y together can do the same work in 20 days. In how many days will Z alone finish the 60% of the work?
If the mean of five observations x + 1, x + 2, x + 3, x + 4 and x + 5 is 15, then what is the mean of the first three observations?
Amit is walking at a speed of 10 km/hr. After every kilometer, he takes a rest for 5 minutes. What is the time taken to cover a distance of 5 kilometers by Amit?
The difference between cost price (CP) and selling price (SP) of an article is Rs 240. If the profit is 20%, then the selling price is
Consider the following frequency distribution. | Class | 0-10 | 10-20 | 20-30 | 30-40 | 40-50 | 50-60 | 60-70 | |---|---|---|---|---|---|---|---| | Frequency | 4 | 5 | 7 | 10 | 12 | 8 | 4 | Find the median of the distribution?
Work through every CUET UG Arithmetic PYQ, year by year.